3,345 km of expressway is open and the state wants private capital for the next 2,800 km. Who owns the toll roads, how the tolls and risk sharing work, and where an outside investor can enter.
1,163 km of expressway at the end of 2020 became 3,345 km at the end of 2025. Another 2,111 km was under construction in May 2026.
2,485 km came from the state budget and 860 km from PPP. For 2026-2030 the ministry counts US$50.7B of expressway capital, of which US$33.8B is not yet raised.
The state can fund up to 70% of a PPP road and pays half of a revenue shortfall below 75% of plan. Tolls on state-built roads started in March 2026.
Vietnam passed its 3,000 km target and closed 2025 with 3,345 km of expressway main routes. Only 1,238 km is full standard; 1,559 km is limited four-lane and 548 km is two-lane, so widening is the next programme.
The ministry puts 2026-2030 expressway capital at about VND 1,269 trillion (US$50.7B) for 2,830 km of new road and 1,190 km of upgrades. About two thirds is unfunded. A pipeline of 29 PPP expressways worth US$35B is in the market.
54 BOT projects collected VND 16,236B in 2025. VEC, VIDIFI, Deo Ca and CII hold the roads that carry the traffic. Hanoi-Hai Phong alone collected about VND 3,852B.
Bac Giang-Lang Son collects 42% of its planned revenue. Eleven BOT projects are proposed for support or early termination. Decree 122/2026 gives older contracts a legal route to share the shortfall.
Metro Pacific bought about 45% of CII Bridges and Roads in 2015 and NEXCO took 20% of a single BOT in 2017. The 2025-2026 deals are IFC into electronic tolling and MSC and APM Terminals into ports.
Another 2,111 km was under construction in May 2026
• Main routes only. With interchanges and access roads the ministry counts about 3,803 km.
Open, under construction and planned expressways, with the airports, ports and ring roads named in this report
The budget built 74% of the existing network. The next phase is offered to private investors
Six rules that set the cash flow of a Vietnamese toll road
| Rule | What it says | Basis |
|---|---|---|
| State capital in a PPP road | Ceiling raised from 50% to 70% of total investment under set conditions. Build-transfer contracts return. | Law 90/2025/QH15, June 2025 |
| Revenue risk sharing | Below 75% of planned revenue, the state pays half of the gap up to 75%. Above 125%, the project company pays the state half of the excess. | PPP Law, Article 82 as amended |
| Older BOT contracts in shortfall | Contracts signed before 2021 can now share a shortfall or be terminated early with compensation, based on the last three years of revenue and a State Audit review. | Decree 122/2026, April 2026 |
| Tolls on state-built expressways | VND 1,300 per vehicle-km on full-standard four-lane roads and VND 900 on lower-standard sections. Charging began on 2 March 2026 and covered 15 sections by August. | Decree 130/2024 |
| BOT toll increases | The rule allows 12% to 18% every three years. Increases due from 2019 were held back until 29 December 2023, when 41 projects were raised together. | Circular 159/2013 |
| Electronic toll collection | Mandatory on all expressways since 1 August 2022. More than 8 million vehicles carry a tag. VETC, owned by Tasco, holds about 75% of the market. | Ministry of Construction, October 2026 |
State-built expressways collected about VND 3,168B from nearly 34 million vehicle passes between March and 12 October 2026, above plan. That is the first traffic record on roads that had been free, and it is the evidence base for the toll-rights auctions.
Revenue is concentrated on the Hanoi and Ho Chi Minh City corridors, and 11 projects are in line for state support
More than 254 million vehicles passed BOT stations in 2025.
Revenue is about VND 52B a month against a plan of VND 123B. The road cost VND 12,189B with 13.5% equity. The province has asked for VND 4,580B of central budget support, the investor return was cut from 11.5% to 9.34%, and the loan rate from 10.5% to 8.53%.
One state corporation, three listed groups and a short list of private builders
| Operator | Roads | Latest figures |
|---|---|---|
| Vietnam Expressway Corporation (VEC), state-owned | Noi Bai-Lao Cai, Cau Gie-Ninh Binh, HCMC-Long Thanh-Dau Giay, Da Nang-Quang Ngai, Ben Luc-Long Thanh. About 540 km. | 2025 net revenue VND 6,901B (+16%); profit after tax above VND 1,050B |
| Deo Ca Traffic Infrastructure (HHV), listed, Deo Ca Group | Deo Ca, Co Ma, Cu Mong and Hai Van tunnels; Bac Giang-Lang Son; Cam Lam-Vinh Hao; Dong Dang-Tra Linh. 472 km of roads and 31 km of tunnels under management. | 2025 toll revenue VND 2,106B (+10%); net profit VND 678B |
| Ho Chi Minh City Infrastructure Investment (CII), listed | Trung Luong-My Thuan and urban toll assets in Ho Chi Minh City. Trung Luong-My Thuan carried 10.1 million vehicles in 2025. | 2024 toll revenue above VND 2,560B |
| VIDIFI, state-linked | Hanoi-Hai Phong, 105 km. About 65,000 vehicles a day, 3.6 times the 2016 level. | 2025 toll revenue about VND 3,852B, the highest of any BOT road |
| Tasco (HUT), listed | BOT roads and VETC, the main electronic tolling operator: 136 stations and 765 lanes. | VETC 2025 revenue VND 666B (+35%) |
| Phuong Thanh, private | Leads the Hanoi-Thai Nguyen-Cho Moi BOT, 99 km, VND 21,229B. | Bid in 2025 to widen the North-South expressway under PPP |
Bank loans run 10 to 12 years against toll periods of about 20
| Term | Level | Evidence |
|---|---|---|
| Return on equity in the financial plan | 11.5% to 12.5% | HCMC-Trung Luong-My Thuan expansion 11.77%; Highway 1 Hanoi-Bac Giang 12.53%. Negotiated per contract, not set by law. |
| Loan interest in the financial plan | 10.5% to 11.8% | Dong, floating. |
| Leverage | About 85% debt | HCMC-Trung Luong-My Thuan expansion: VND 36,172B, 15% equity, six banks led by VietinBank. |
| Toll period | 17 to 29 years | About 20 years is typical. |
| Bank loan tenor | 10 to 12 years | Shorter than the toll period, so refinancing risk sits with the sponsor. |
| Cost against a public project | 30% to 50% higher | Interest and investor return, as stated in the National Assembly in April 2026. |
Disclosed foreign transactions in Vietnamese toll roads and transport infrastructure
| Year | Investor | Target | Terms |
|---|---|---|---|
| 2015 | Metro Pacific Tollways (Philippines) | CII Bridges and Roads | About 45% through shares and exchangeable bonds, VND 1.95 trillion (US$91M). Exit announced in 2024. |
| 2017 | NEXCO Central and JEXWAY (Japan) | Phu Ly bypass BOT, FECON | 20% stake in a project of about US$97M. |
| 2025 | IFC | VETC, Tasco | VND 500B (US$19M) convertible bond for electronic tolling. |
| 2026 | Hateco with APM Terminals | Lien Chieu container port, Da Nang | Won the concession; about US$1.7B. Ground broken in April 2026. |
| 2026 | VIMC, Saigon Port and TIL (MSC) | Can Gio transshipment port | TIL 49%, VIMC 36%, Saigon Port 15%; about VND 128.9 trillion. |
Cost and status of the projects that change traffic patterns around the two main cities
| Project | Cost | Status |
|---|---|---|
| Long Thanh International Airport, phase 1 | US$4.2B to 4.4B | Commercial flights set to begin on 24 December 2026. Capacity 25 million passengers a year. |
| Ho Chi Minh City Ring Road 3 (76 km) | VND 75,300B | About 76% built in November 2026. Full route targeted for the end of 2026. |
| Ho Chi Minh City Ring Road 4 | VND 120.4 trillion | BOT, ten sub-projects. First component started in June 2026. Target 2028. |
| Hanoi Ring Road 4 | VND 85.8 trillion | PPP expressway component started in September 2025. Target November 2027. |
| Bien Hoa-Vung Tau expressway (54 km) | VND 17.8 trillion | Fully open since 18 May 2026. |
| Ben Luc-Long Thanh expressway (58 km) | VEC | Full opening with Phuoc Khanh bridge at the end of September 2026. |
| HCMC-Moc Bai expressway (51 km) | VND 19,617B | BOT component started in July 2026. Target December 2027. |
| Chau Doc-Can Tho-Soc Trang (188 km) | VND 44,691B | First 57 km open since December 2025. Full route now July 2027. |
| Lao Cai-Hanoi-Hai Phong railway | VND 289 trillion | Started in December 2025. Budget raised in August 2026. |
| North-South high-speed railway | US$67B | Ground-breaking moved to December 2027. Vingroup withdrew its bid in December 2025. |
| Gia Binh airport | US$7.5B | Developer Masterise. Started in August 2025. Target 2027. |
| HCMC metro line 2 (11 km) | VND 47.8 to 57 trillion | Started in January 2026. Target 2030. |
Car ownership was about 68 per 1,000 people at the end of 2024
Operating roads price on traffic history; roads under construction carry land, cost and ramp-up risk
Several operating roads under one holding company spread traffic risk. Metro Pacific used this route in 2015. The buyer depends on the sponsor for governance and on dividends for cash.
Convertible or preferred capital sits between 85% bank debt and thin sponsor equity. Bank loans mature in 10 to 12 years, so the sponsor needs capital that waits longer.
The pilot auctions announced in November 2026 sell the right to collect on finished North-South sections. Tolling began in March 2026, so the traffic record is short.
GA Capital advises on toll road and expressway transactions in Vietnam. Material on current transactions is shared with qualified investors under a confidentiality agreement.