GA Capital
Vietnam FIT Update — GA Capital
Back to Insights
Vietnam renewable energy policy and tariff framework
GA Capital | Policy Update

Vietnam FIT Update

2025 Tariff Regime

From fixed FiTs to cost-based IRR caps: how the new PPA mechanism works, what it means for USD equity returns, and why projects still pencil.

November 2025
GA Capital Research
Vietnam FIT Update

Need to Know

1

No More FiTs

Fixed USD tariffs ended Oct 2021. Post-2025, tariffs are cost-based with a 12% VND project IRR cap, subject to MOIT price ceilings.

2

Limited Indexation

70–85% of revenue (capex recovery) is fixed in nominal VND with no CPI protection. O&M indexed ~2.5% p.a.; FX adjustment on foreign debt only.

3

USD IRR Reality

Headline 12% VND IRR → ~5–9% USD equity IRR after inflation, FX erosion, and limited indexation. Optimize via cost control and capital structure.

Executive Summary

01

Two tariff regimes

Retail tariffs (what consumers pay EVN) adjust based on EVN costs — not your concern. Generation tariffs (what EVN pays your project) are governed by MOIT ceilings + cost-based models with a 12% VND IRR cap.

02

PPA price pinned between cost model and ceiling

Your negotiated tariff must: (1) be computed from a regulated cost model (capex, O&M, financing), (2) deliver project IRR ≤ 12% in VND, and (3) not exceed the annual MOIT price ceiling for your tech/region.

03

Fixed capex recovery, limited O&M indexation

Wind PPA price = FC (capex) + FOMC (O&M). FC is ~70–85% of revenue, fixed in nominal VND with no CPI/FX hedge. FOMC gets ~2.5% p.a. indexation; FX adjustment covers foreign debt principal only.

04

12% VND ≠ 12% USD

After 3–4% VND inflation, 2–3% depreciation, and capped O&M indexation, a headline 12% VND project IRR translates to ~5–9% USD equity IRR depending on macro and execution.

05

Projects still work via angles

Build below normative costs (real IRR > 12%), leverage local debt, bet on stable macro, treat as platform/M&A exit, or use USD debt with FX pass-through on loan principal.

Tariff Framework

Two different 'prices' in Vietnam

Retail vs generation: what matters for wind and solar developers

Retail Tariff Mechanism

Adjusts based on EVN actual costs; tariffs can move up or down if costs shift significantly.

Who it affects:

Households and factories (end consumers)

Key features:
  • Cost-reflective mechanism
  • Responds to EVN operational costs
  • Not relevant for wind or solar developers
  • Background context only
Basis: New retail tariff adjustment framework (2025)

Generation / PPA Tariff

What EVN pays renewable generators; governed by MOIT price brackets and new PPA rules.

Who it affects:

Wind and solar project developers

Key features:
  • No fixed FiT post-2025
  • Annual MOIT price ceiling by tech/region
  • Tariff must deliver project IRR ≤ 12% (VND)
  • Cost-based model mandatory
  • Must not exceed MOIT ceiling
Basis: Circular 12/2025 (MOIT), Decree 57/2025 (DPPA framework), Annual price ceiling announcements
PPA Structure

EVN PPA tariff for wind: fixed capex + indexed O&M

Price components and their share of total revenue

Fixed Cost (Capex Recovery) (FC)

70–85%

Recovers capital expenditure over contract term

Not Indexed
  • Fixed in nominal VND once agreed
  • No CPI or FX protection
  • Real value erodes with inflation
  • Largest component of tariff

Fixed O&M (FOMC)

15–30%

Fixed operations & maintenance costs

IndexedCap: ~2.5% p.a.
  • Adjusted annually by cost/CPI/wage indices
  • Capped at approximately 2.5%/year
  • Provides limited inflation protection
  • Smaller component of total tariff

FX Adjustment (Debt) (FX_adj)

Variable

Compensates for exchange rate changes on foreign loan principal

Indexed
  • Only applies to foreign currency borrowings
  • Covers loan principal changes, not interest
  • Reduces currency mismatch on debt
  • Equity remains VND-exposed

FC = capex recovery (fixed cost); largest component, fixed in nominal VND over 20 years.

FOMC = fixed O&M; indexed annually but capped at ~2.5% p.a.

FX adjustment applies only to foreign currency debt principal, not full tariff.

Why this matters: 70–85% of your revenue has zero inflation or FX protection; real value erodes over time unless you build in cushion or optimize execution.

IRR Framework

12% project IRR cap — on normative costs, not actuals

The regulatory model calculates a 12% VND project IRR using 'reasonable' capex, O&M, and financing assumptions. If you build and operate cheaper than these normative costs, your real project IRR can exceed 12%. This gap is where value is created under the new regime.

Wind and solar project construction illustrating cost optimization
Cost discipline: building below normative assumptions can lift real returns above the 12% regulatory cap.
Indexation Mechanics

What moves and what doesn't

The revenue stack: most is frozen in nominal VND

What IS indexed

  • O&M component (FOMC): Allowed to increase each year by cost / CPI / wage indices, but generally capped at ~2.5% p.a.
  • FX on foreign loans: Adjustment compensates for exchange-rate changes on loan principal if you borrow in USD or other foreign currencies.

What is NOT indexed

  • Capex recovery (FC): Fixed in nominal VND once agreed; no CPI or FX protection.
  • Full tariff indexation: No comprehensive CPI escalator on the entire tariff.
  • Ceiling adjustments: If MOIT raises price ceiling in later years, existing PPAs do not automatically adjust upward.

Revenue Split Summary

70–85% Fixed (No protection)

Capex recovery in nominal VND

15–30% Partially indexed

O&M (~2.5% cap) + FX on debt

Capex recovery (FC) = largest share, no indexation → inflation & FX erode real value.

O&M (FOMC) gets cost/CPI/wage adjustment but capped at ~2.5% p.a. → partial protection.

FX adjustment on foreign debt principal helps reduce currency mismatch on loan side, but equity cash flows remain VND-exposed.

If MOIT raises future price ceilings, existing PPAs do not automatically move up.

Why this matters: over 20 years, VND depreciation and inflation above 2.5% compress your USD-equivalent IRR unless you front-load value or optimize structure.

Regime Comparison

FiT era vs 2025+ cost-based regime

What changed and what it means for project economics

AspectFiT Era (pre-2021)Current Regime (2025+)
Pricing StructureFixed US¢/kWh rates set by governmentCost-based model with IRR ≤ 12% cap + MOIT ceiling
Tariff Duration20 years at fixed rate20 years with single fixed or scheduled prices
IndexationNone (full USD FiT, no adjustment)Limited: O&M ~2.5% cap + FX on debt only
Revenue CertaintyHigh (fixed USD tariff)Moderate (VND exposed, limited indexation)
FX ProtectionFull (denominated in USD)Partial (only on foreign debt principal)
IRR FrameworkImplicit (market set FiT)Explicit 12% cap on normative costs
Price DiscoveryGovernment-set, technology-specificNegotiated within cost model + ceiling constraints
Return Analysis

12% VND → 5–9% USD: scenario walkthrough

How headline VND IRR translates to USD equity returns

ScenarioVND IRRInflationFX DepreciationImplied USD IRRCommentary
Base (Regulatory)12.0%3.0%2.0%7.0%Headline 12% VND project IRR; after inflation & FX, USD equity returns ~7%.
Optimistic12.0%2.5%1.5%8.5%Lower macro headwinds; USD returns improve to mid–high single digits.
Pessimistic12.0%4.0%3.0%5.0%Higher inflation & depreciation; USD equity IRR compresses to low single digits.
Cost Optimization14.5%3.0%2.0%9.5%Build below normative costs; real project IRR exceeds 12% cap, lifting USD returns.
Base (Regulatory)
7 %
Optimistic
8.5 %
Pessimistic
5 %
Cost Optimization
9.5 %

Base scenario: 3% VND inflation, 2% depreciation, O&M capped at 2.5% p.a. → ~7% USD IRR.

Optimistic: lower inflation (2.5%), lower FX (1.5%) → ~8.5% USD IRR.

Pessimistic: higher inflation (4%), higher FX (3%) → ~5% USD IRR.

Cost optimization: build below normative costs → real project IRR ~14.5% → ~9.5% USD IRR.

Why this matters: headline 12% VND cap is not your true return; macro assumptions and execution drive actual USD equity IRR.

Value Creation

Why projects still pencil: the angles

How developers make 10–12% VND IRR work in practice

1

Normative Cost vs Actual Cost

Build and operate below the reasonable or allowed costs in regulator model

Impact

Real project IRR can exceed 12% cap, improving USD equity returns

Applicability
  • Local EPC advantages
  • Supply chain optimization
  • Efficient O&M
2

Capital Structure & Local Debt

Leverage cheaper local bank debt and lower return expectations

Impact

Reduces financing costs, improves project economics

Applicability
  • Vietnamese sponsors
  • Local bank relationships
  • VND borrowing
3

Macro Assumptions

Conservative inflation/FX assumptions improve downside protection

Impact

Less FX/inflation erosion → better real USD returns

Applicability
  • Stable macro outlook
  • SBV credibility
  • Moderate inflation
4

Strategic / Platform Value

Early market entry builds relationships, track record, and pipeline

Impact

Platform premium on exit; optionality if policy improves

Applicability
  • First-mover advantage
  • M&A exit strategy
  • Portfolio building
5

USD Debt with FX Pass-Through

Use USD project finance from DFIs/foreign banks with PPA FX adjustment

Impact

Reduces debt-side currency mismatch; equity still VND-exposed

Applicability
  • DFI support
  • Foreign lenders
  • Large-scale projects

Normative vs actual: regulator uses "reasonable" costs; if you build cheaper, real IRR > 12%.

Local advantages: Vietnamese groups have cheaper debt, lower return expectations, and EPC synergies.

Platform value: early entry = relationships, track record, M&A premium on exit.

USD debt with FX pass-through reduces loan-side currency mismatch; equity still VND-exposed.

Why this matters: headline 12% cap is not a hard ceiling on real returns; execution and structure unlock upside.

DPPA Context

DPPA vs EVN PPA: flexibility within bounds

Corporate DPPAs offer more shape flexibility but same ceiling constraint

DimensionEVN PPADPPANotes
Price StructureCost-based, IRR ≤ 12%, price ≤ MOIT ceilingNegotiated, but price still ≤ MOIT ceilingDPPA offers more flexibility on shape, but ceiling binds both
EscalationLimited: O&M ~2.5% cap + FX on debtNegotiable within regulatory boundsDPPA can theoretically allow richer escalation, subject to offtaker credit
Counterparty RiskEVN (state utility); low default riskCorporate offtaker; credit-dependentDPPA requires bankable corporate; EVN is safer but less flexible
Volume / CurtailmentEVN dispatch; curtailment risk presentDirect delivery or virtual; terms negotiableDPPA can specify must-take or curtailment penalties
Price DiscoveryRegulator-driven (cost model + ceiling)Market-driven within ceiling constraintDPPA allows for competitive dynamics, but ceiling still caps upside

Both DPPA and EVN PPA must not exceed MOIT price ceiling for tech/region.

DPPA can negotiate escalation terms, but corporate credit and regulatory bounds still constrain economics.

EVN PPA = safer counterparty (state utility), less flexible terms.

DPPA = market-driven pricing within ceiling, but requires bankable corporate offtaker.

Why this matters: DPPAs are not a magic bullet; ceiling still caps upside, and corporate credit matters.

Policy Evolution

Policy timeline: from FiTs to cost-based IRR caps

Key regulatory milestones shaping the 2025+ tariff regime

Mar 3, 2025decree

Decree 57/2025/NĐ-CP — Full DPPA Framework

  • Enables direct power purchase agreements between generators and large consumers
  • Price must not exceed MOIT ceiling for tech/region
  • Flexibility on escalation terms within regulatory bounds
  • Corporate offtake for creditworthy buyers
Impact

Opens corporate DPPA pathway alongside EVN PPAs; price discovery still constrained

Jan 15, 2025circular

Circular 12/2025/TT-BCT — PPA Tariff Mechanism

  • Cost-based tariff calculation mandatory
  • Project IRR capped at 12% (VND) on normative costs
  • O&M indexation capped at ~2.5% p.a.
  • FX adjustment for foreign debt principal only
Impact

Replaces fixed FiTs with IRR-capped, cost-based pricing; limits upside but provides structure

Jul 3, 2024decree

Decree 80/2024/NĐ-CP — Transitional DPPA

  • Introduced initial DPPA framework
  • Bridge between FiT expiry and new mechanism
  • Set foundation for Decree 57 refinements
Impact

Early DPPA adopters (e.g., LEGO Sep 2025) operated under this framework

Jan 7, 2023decision

Decision on Ceiling Prices — Solar & Wind

  • Solar ground: 5.05 US¢/kWh; floating: 6.43 US¢/kWh
  • Onshore wind: 6.77 US¢/kWh; offshore: 7.75 US¢/kWh
  • Applied to transitional projects pending new PPA rules
Impact

Lower than legacy FiTs; compressed revenue expectations for 2023-2024 projects

Tariff Evolution

Tariff regime timeline: FiTs → ceilings → cost-based IRR

How headline rates and mechanisms have changed

PeriodMechanismSolar RangeWind RangeNotes
2017–2021Fixed FiTs7.09–9.35 US¢/kWh7.80–9.80 US¢/kWhFixed USD tariffs; high certainty; FiT windows closed Oct 2021
2023 (Transitional)Ceiling Prices5.05–6.43 US¢/kWh6.77–7.75 US¢/kWhLower caps for transitional projects; no indexation
2025+Cost-based + IRR CapCost model, IRR ≤ 12% VND, ≤ MOIT ceilingCost model, IRR ≤ 12% VND, ≤ MOIT ceilingLimited indexation (O&M ~2.5%, FX on debt); 20-year term

FiT era: fixed USD rates, high certainty, windows closed Oct 2021.

2023 transitional: ceiling prices lower than legacy FiTs, applied to transitional projects.

2025+ regime: cost-based model with 12% VND IRR cap + MOIT ceiling; limited indexation.

Why this matters: tariff structure has shifted from high-certainty USD FiTs to lower-certainty VND cost-based pricing; project economics require more sophisticated modeling and optimization.

References

Sources