GA Capital
Insights
GA CapitalNovember 2025

GA Capital · Vietnam Renewables

Post-FiT TariffMechanics

Investment thesis

Fixed FiTs closed in 2021. New EVN PPAs price off cost models with a 12% VND IRR cap, MOIT ceilings, and limited indexation on O&M.

POLICY READ

Need to Know

01

FiTs ended

Fixed USD tariffs closed Oct 2021. Post-2025 PPAs use cost-based pricing capped at 12% VND project IRR and MOIT ceilings.

02

Capex is frozen

70–85% of tariff revenue (capex recovery) sits in nominal VND with no CPI or FX hedge. O&M indexed ~2.5% p.a.; FX adjustment covers foreign debt principal only.

03

USD returns compress

Headline 12% VND IRR translates to ~5–9% USD equity after inflation, depreciation, and indexation caps. Execution and capital structure drive where a deal lands.

Executive Summary

01

Two tariff layers

Retail tariffs track EVN cost recovery for consumers. Generation PPAs for wind and solar use MOIT ceilings plus cost-based models capped at 12% VND IRR.

02

PPA price sits between model and ceiling

Negotiated tariff must follow the regulated cost stack, deliver ≤12% VND IRR on normative assumptions, and stay under the annual MOIT ceiling for technology and region.

03

Capex recovery is nominal VND

Wind PPA = FC (capex) + FOMC (O&M). FC is ~70–85% of revenue, fixed without CPI/FX protection. FOMC rises ~2.5% p.a.; FX adjustment covers foreign debt principal only.

04

12% VND ≠ 12% USD

With 3–4% inflation, 2–3% depreciation, and capped O&M indexation, headline VND IRR converts to ~5–9% USD equity depending on macro and execution.

05

Deals still close on execution

Below-normative build cost, local debt, stable macro, platform/M&A exit, or USD debt with FX pass-through on principal remain the main levers.

Tariff Framework

Retail and PPA tariffs move on different rules

Generation pricing is what matters for wind and solar offtake

InstrumentMechanismRelevanceKey features
Retail tariffEVN adjusts end-user tariffs when its cost base moves materially. This layer does not set renewable PPA prices.Households and industrial consumers
  • Cost-reflective retail adjustment
  • Tracks EVN operating and fuel costs
  • Background context for power-sector economics
Generation / EVN PPAWhat EVN pays wind and solar generators under MOIT price ceilings and Circular 12/2025 cost-based rules.Wind and solar developers on EVN offtake
  • No fixed FiT post-2025
  • Annual MOIT ceiling by technology and region
  • Tariff must deliver project IRR ≤ 12% (VND) on normative costs
  • Cost-based model mandatory
  • Cannot exceed MOIT ceiling
PPA Structure

EVN wind PPA splits fixed capex from indexed O&M

FC dominates revenue; indexation is partial

Fixed Cost (Capex Recovery) (FC)

70-85%

Recovers capital expenditure over the contract term

Indexation: None (nominal VND)

  • •Fixed in nominal VND once agreed
  • •No CPI or FX protection
  • •Real value erodes with inflation
  • •Largest component of tariff

Fixed O&M (FOMC)

15-30%

Fixed operations and maintenance costs

Indexation: Yes, capped at ~2.5% p.a.

  • •Adjusted annually by cost/CPI/wage indices
  • •Capped at approximately 2.5%/year
  • •Partial inflation protection only
  • •Smaller share of total tariff

FX Adjustment (Debt) (FX_adj)

Variable

Compensates for exchange-rate changes on foreign loan principal

Indexation: Yes

  • •Applies to foreign-currency borrowings only
  • •Covers loan principal changes, not interest
  • •Reduces currency mismatch on debt
  • •Equity cash flows remain VND-exposed

• FC = capex recovery, fixed in nominal VND over 20 years.

• FOMC = fixed O&M, indexed annually but capped at ~2.5% p.a.

• FX adjustment applies to foreign-currency debt principal, not the full tariff.

• 70–85% of revenue carries zero inflation or FX protection over the contract term.

IRR Framework

12% cap applies to normative costs, not actual build cost

The regulatory model calculates a 12% VND project IRR using reasonable capex, O&M, and financing assumptions. Projects built and operated below those normative costs can exceed 12% in practice. That gap is where value is created under the new regime.

Wind and solar project construction in Vietnam
Cost discipline below normative assumptions can lift real returns above the 12% regulatory cap.
Indexation Mechanics

Most tariff revenue sits in nominal VND

O&M and debt FX provide partial protection only

ComponentIndexed?Detail
O&M (FOMC)PartialAllowed to increase by cost/CPI/wage indices, capped at ~2.5% p.a.
FX on foreign loansYesAdjusts for exchange-rate changes on loan principal for USD or other foreign borrowings.
Capex recovery (FC)NoFixed in nominal VND once agreed; no CPI or FX protection.
Full tariff escalatorNoNo comprehensive CPI escalator on the entire tariff.
Ceiling upliftNoExisting PPAs do not automatically move up if MOIT raises future ceilings.
70–85% fixed (no protection)

Capex recovery in nominal VND

15–30% partially indexed

O&M (~2.5% cap) + FX on debt

• Capex recovery (FC) is the largest share and carries no indexation.

• O&M (FOMC) adjusts by cost/CPI/wage indices but is capped at ~2.5% p.a.

• FX adjustment on foreign debt principal reduces loan-side mismatch; equity remains VND-exposed.

• Higher MOIT ceilings in later years do not automatically lift existing PPAs.

Regime Comparison

FiT era vs 2025 cost-based regime

Certainty, indexation, and FX protection all narrowed

AspectFiT Era (pre-2021)Current Regime (2025+)
Pricing StructureFixed US¢/kWh rates set by governmentCost-based model with IRR ≤ 12% cap + MOIT ceiling
Tariff Duration20 years at fixed rate20 years with single fixed or scheduled prices
IndexationNone (full USD FiT, no adjustment)Limited: O&M ~2.5% cap + FX on debt only
Revenue CertaintyHigh (fixed USD tariff)Moderate (VND exposed, limited indexation)
FX ProtectionFull (denominated in USD)Partial (only on foreign debt principal)
IRR FrameworkImplicit (market set FiT)Explicit 12% cap on normative costs
Price DiscoveryGovernment-set, technology-specificNegotiated within cost model + ceiling constraints
Return Analysis

Headline 12% VND clears ~5–9% USD equity

Macro assumptions and build cost drive the spread

ScenarioVND IRRInflationFX DepreciationImplied USD IRRCommentary
Base (Regulatory)12.0%3.0%2.0%7.0%Headline 12% VND project IRR; inflation and FX compress USD equity to ~7%.
Optimistic12.0%2.5%1.5%8.5%Lower macro drag lifts USD equity into high single digits.
Pessimistic12.0%4.0%3.0%5.0%Higher inflation and depreciation push USD equity toward ~5%.
Cost Optimization14.5%3.0%2.0%9.5%Build below normative costs; real project IRR exceeds the 12% regulatory cap.
Base (Regulatory)
7 %
Optimistic
8.5 %
Pessimistic
5 %
Cost Optimization
9.5 %

• Base: 3% VND inflation, 2% depreciation, O&M capped at 2.5% p.a. → ~7% USD IRR.

• Optimistic: lower inflation (2.5%), lower FX (1.5%) → ~8.5% USD IRR.

• Pessimistic: higher inflation (4%), higher FX (3%) → ~5% USD IRR.

• Cost optimization: build below normative costs → real project IRR ~14.5% → ~9.5% USD IRR.

Value Creation

Five levers that clear 12% VND in practice

Normative cost gap, capital structure, and exit shape the outcome

LeverMechanismEffect
Normative vs actual costBuild and operate below the reasonable costs in the regulator modelReal project IRR can exceed the 12% cap and lift USD equity returns
Local debt and capital structureCheaper local bank debt and lower sponsor return hurdlesFinancing cost reduction improves project economics
Conservative macro assumptionsUnderwriting assumes higher inflation and FX erosion than base caseDownside protection if macro stays stable
Platform / M&A exitEarly entry builds relationships, track record, and pipelinePlatform premium on exit; optionality if policy improves
USD debt with FX pass-throughDFI or foreign-bank project finance with PPA FX adjustment on principalReduces debt-side currency mismatch; equity stays VND-exposed

• Regulator uses reasonable costs; below-normative build can lift real IRR above 12%.

• Local sponsors often access cheaper debt and lower return hurdles.

• Platform value from early entry can offset compressed tariff returns on exit.

DPPA Context

DPPA adds shape flexibility; ceiling still binds

Corporate offtake does not bypass MOIT price caps

DimensionEVN PPADPPANotes
Price StructureCost-based, IRR ≤ 12%, price ≤ MOIT ceilingNegotiated, but price still ≤ MOIT ceilingDPPA allows more shape flexibility; ceiling binds both
EscalationLimited: O&M ~2.5% cap + FX on debtNegotiable within regulatory boundsDPPA can allow richer escalation subject to offtaker credit
Counterparty RiskEVN (state utility); low default riskCorporate offtaker; credit-dependentDPPA requires bankable corporate; EVN is safer but less flexible
Volume / CurtailmentEVN dispatch; curtailment risk presentDirect delivery or virtual; terms negotiableDPPA can specify must-take or curtailment penalties
Price DiscoveryRegulator-driven (cost model + ceiling)Market-driven within ceiling constraintDPPA allows competitive dynamics; ceiling still caps upside

• Both DPPA and EVN PPA must stay at or below the MOIT ceiling for technology and region.

• DPPA can negotiate escalation terms, but corporate credit and regulatory bounds still constrain economics.

• EVN PPA offers safer counterparty; DPPA requires bankable corporate offtaker.

Policy Evolution

Policy path from FiT expiry to Circular 12/2025

Decree 57 and Circular 12 define the 2025+ framework

Mar 3, 2025decree

Decree 57/2025/NĐ-CP: Full DPPA Framework

  • •Enables direct power purchase agreements between generators and large consumers
  • •Price must not exceed MOIT ceiling for tech/region
  • •Escalation terms negotiable within regulatory bounds
  • •Corporate offtake for creditworthy buyers

Corporate DPPA pathway opens alongside EVN PPAs; ceiling still binds price discovery

Jan 15, 2025circular

Circular 12/2025/TT-BCT: PPA Tariff Mechanism

  • •Cost-based tariff calculation mandatory
  • •Project IRR capped at 12% (VND) on normative costs
  • •O&M indexation capped at ~2.5% p.a.
  • •FX adjustment for foreign debt principal only

Fixed FiTs replaced by IRR-capped, cost-based pricing with limited indexation

Jul 3, 2024decree

Decree 80/2024/NĐ-CP: Transitional DPPA

  • •Introduced initial DPPA framework
  • •Bridge between FiT expiry and new mechanism
  • •Set foundation for Decree 57 refinements

Early DPPA adopters (e.g., LEGO Sep 2025) operated under this framework

Jan 7, 2023decision

Decision on Ceiling Prices: Solar & Wind

  • •Solar ground: 5.05 US¢/kWh; floating: 6.43 US¢/kWh
  • •Onshore wind: 6.77 US¢/kWh; offshore: 7.75 US¢/kWh
  • •Applied to transitional projects pending new PPA rules

Lower than legacy FiTs; compressed revenue expectations for 2023-2024 projects

Tariff Evolution

FiTs → ceiling prices → cost-based IRR caps

Headline rates and indexation narrowed at each step

PeriodMechanismSolar RangeWind RangeNotes
2017-2021Fixed FiTs7.09-9.35 US¢/kWh7.80-9.80 US¢/kWhFixed USD tariffs; high certainty; FiT windows closed Oct 2021
2023 (Transitional)Ceiling Prices5.05-6.43 US¢/kWh6.77-7.75 US¢/kWhLower caps for transitional projects; no indexation
2025+Cost-based + IRR CapCost model, IRR ≤ 12% VND, ≤ MOIT ceilingCost model, IRR ≤ 12% VND, ≤ MOIT ceilingLimited indexation (O&M ~2.5%, FX on debt); 20-year term

• FiT era: fixed USD rates, high certainty; windows closed Oct 2021.

• 2023 transitional ceilings sat below legacy FiTs for bridge projects.

• 2025+ regime: cost-based model with 12% VND IRR cap, MOIT ceiling, limited indexation.

References

Sources